Following an electrical inspection highlighting multiple issues, we planned and executed a comprehensive program of remedial works including a full mains distribution upgrade.

An electrical inspection at a busy commercial and production facility in Wirral revealed critical compliance issues and distribution limitations. The client required urgent remedial action and a modern mains upgrade, but could not afford any daytime operational downtime.
We designed a phased out-of-hours programme. We installed a new three-phase distribution board and condensed multiple legacy consumer units into it. The existing distribution boards were relocated and centralized, and all cabling was rerouted through a new galvanised steel trunking containment system. All work was performed overnight and at weekends.
Completed on schedule with zero interruption to the client's daytime operations. Handed over with a complete NICEIC installation certificate and full circuit labelling for their facility maintenance team.





Earlier we’re involved, fewer surprises on site. We’ll tell you candidly whether we’re the right fit for your project.